There are no Open Network Issues Currently
Sydney Services - Data Centre Migration (Resolved) High

Affecting Server - VPS - Sydney

  • 04/10/2020 21:30 - 05/10/2020 09:32
  • Last Updated 20/09/2020 17:01

04/10/2020 at 10PM AEST - Approx 2-3 hours

The server will be moved from the Equinix data centre to NextDC S2 which is located at Macquarie Park NSW.

This facility is one of the newest from NextDC in Sydney and will significantly improve network capacity and the level of redundancy.

The move is expected to take about 2-3 hours to complete which means there will be 2-3 hours downtime.

Full rollback plans have been organised if required however the network is already established at NextDC S2 and working optimally.

Adelaide and Melbourne services will be unaffected.

Thank you for your patience.